Welcome to the Global Project Site (GPS).  This site is dedicated to keeping the Columbia community informed on the progress of Columbia Global Commons as it moves toward completion.  It also will provide content related to the development of the Global Commons.  The GPS will include weekly discoveries of Columbia’s global enterprises locally and abroad. 

We welcome and encourage your ideas, thoughts and feedback.

Milestone

Date

Phase 1

 

Approval of Strategy

March 14

First Columbia Global Commons Working Group

TBD

Presentation of Design Decks by mStoner

April 9

Copy Decks Delivered

April 20

Decision on Design Concept

April 25

Final Approval of Template Suite

May 22

Phase 2

 

Start of Drupal Installation and Set-Up

June 8

HTML Approval

June 18

Copy Decks Approval

June 21

Drupal Ready for Content

August 16

Phase 3

 

Training for Content Editors

August 16

Content Migration Begins

August 16

Soft Launch of Columbia Global Commons

September 13

Usability Testing Complete

September 17

Launch of Columbia Global Commons

September 19